What does it mean for a battery to help form the grid instead of simply following it? The answer is more specific than a new inverter setting—and more limited than some product claims suggest. Grid-forming control can help an inverter maintain a stable voltage reference when the surrounding system is weak or disturbed. Whether that capability becomes a useful grid service depends on the battery, inverter, plant controls, protection scheme, operating reserve and interconnection point working together.
Grid-forming is a control behavior, not a product label
A conventional grid-following inverter uses the grid’s voltage waveform as its reference and injects controlled current. A grid-forming inverter instead regulates an internal voltage phasor over the fast time frame, responding to changes in the surrounding system while coordinating active and reactive power. NREL’s UNIFI specification describes this as maintaining a nearly constant internal voltage phasor in the sub-transient to transient period [1]. The distinction matters most where system strength is low, or where the grid is changing quickly.
That does not mean a grid-forming inverter can deliver unlimited fault current, energy or stability. Its semiconductor ratings and current limits still apply. Its energy response depends on what sits behind the inverter: a battery with available state of charge, wind with available input, or solar with available irradiance. NERC’s functional specification stresses that the amount of grid-forming capacity needed is system-specific; percentages from individual studies are not universal planning rules [2].

Storage can supply the buffer, but the operating design decides the service
Battery energy storage is a natural platform because it can change power quickly and store energy for later use. Yet the same megawatt-hour cannot be promised simultaneously to energy arbitrage, contingency response, frequency support and restoration. The project must reserve enough power and energy for the service it sells, across the state-of-charge range in which the grid may call on it. The controls must also resolve conflicts between a market dispatch instruction, battery protection and a grid-stability response.
Batteries are a practical early platform, but the underlying control idea can also apply to wind, solar-plus-storage, microgrids and power-electronic grid assets. That changes the product question: is the customer buying a battery, an inverter, or an operating capability from an integrated plant? A standalone inverter supplier may prove a control response while leaving energy availability, plant-level coordination and restoration sequencing to the owner. A complete offer must make those boundaries visible.
Black start and island operation need their own design basis. A grid-forming mode alone does not guarantee that a plant can energize a dead bus, pick up transformer inrush, carry auxiliary loads or coordinate protection. NREL’s specification treats black start as an optional capability requiring additional design, hardware and coordination with system operators [1]. Buyers should ask for the tested sequence, not accept the feature name as evidence.
Specify the plant response that the grid actually needs
For product teams, the opportunity is to translate a broad grid need into a clear, testable performance envelope. Start with the use case: fast voltage support in a weak network, frequency response, operation through a disturbance, planned islanding, or system restoration. Then specify the conditions and limits: voltage and frequency ranges, current magnitude and duration, active and reactive power priorities, available state of charge, recovery behavior and interactions with protection devices.
The inverter is only one layer. The plant controller, energy-management system, battery-management system, transformer, switchgear, protection, communications and grid operator’s settings all influence the delivered response. Model quality matters too. NERC’s 2025 guideline for electromagnetic-transient studies highlights the need for detailed modeling when evaluating inverter-based resources [3]. The practical product package should therefore include usable plant-level RMS and EMT models, validated against the configured controls, plus factory, hardware-in-the-loop and commissioning tests tied to the promised service.
Teams should distinguish three operating states in the sales and engineering documents: the plant is capable of the function; the function is enabled and accepted by the system operator; and the resource is available to deliver it at the moment of need. Those states can differ because of firmware configuration, study restrictions, maintenance, energy reserve or a market dispatch. Reporting only installed MW with a GFM-capable inverter can therefore overstate the reliability value that the operator can count on.

The commercial case depends on proof and payment
The market is moving toward more explicit expectations for inverter-based resources. In July 2025, FERC approved ride-through reliability standards for inverter-based generators, following its broader Order 901 direction to address data sharing, model validation, planning and operational studies, and performance requirements [4], [5]. This is a higher reliability bar, not a guarantee that every grid-forming capability will earn a separate payment.
A credible commercial offer should connect the incremental cost of controls, testing, energy reservation and warranty exposure to a defined revenue or project benefit. That may come through an ancillary-service market, a capacity or availability contract, an interconnection requirement, a utility procurement, or avoided system-strength equipment. If the buyer cannot specify the response or measure its availability, the capability risks becoming an unpriced feature bundled into the battery bid.
GFM also needs a fair comparison with other solutions. Depending on the location and event, a synchronous condenser may address short-circuit strength, a STATCOM may target dynamic voltage support, grid reinforcement may relieve a network constraint, or an improved grid-following plant may meet the applicable requirement. These options differ in energy duration, fault-current behavior, siting, lead time and operating value. The right comparison is a system study and lifecycle-cost case, not a technology-versus-technology slogan.
Build for the constraint, then verify the claim
The strongest product strategy is not to enable grid-forming mode everywhere by default. It is to identify the network condition, define the service needed, and select the combination of inverter controls, storage duration, power reserve, plant controls and protection that can meet it. NERC recommends system-specific studies and testing, while also urging planners and owners to consider the capability in new battery projects [2]. The commercial decision should remain grounded in the local network study and procurement rules.
For developers and utilities, the buying question is simple: what behavior will this plant deliver at the point of interconnection, under what conditions, and how will we prove it? For manufacturers, the opportunity lies in making that answer specific, model-backed and supportable across the project’s life. Grid-forming inverters may become an important grid resource. Their durable value will come from verified performance that operators can rely on and customers can contract—not from the label alone.
Sources
- UNIFI Specifications for Grid-Forming Inverter-Based Resources, Version 2 (NREL, March 2024).
- White Paper: Grid Forming Specifications (NERC, September 2023).
- Reliability Guideline: Electromagnetic Transient Studies for Interconnection of Inverter-Based Resources (NERC, March 2025).
- FERC Approves Grid Reliability Standards Applicable to Inverter-Based Generators (FERC, July 2025).
- Order No. 901: Reliability Standards to Address Inverter-Based Resources (FERC, October 2023).